Bellevue Skate Plaza Opens September 7, 2012 The opening day is finally here! Tomorrow will be the grand opening Pittsburgh’s newest public skateboard plaza. Head on down to Bayne Park in Bellevue…34 N Balph Pittsburgh, PA 15202.… Read More
Concrete is Curing, Grand Opening Date to be Announced Grand opening of the Bellevue, PA Skate Plaza at Bayne Park is coming soon! We will let you know when we get the official word from council.… Read More
Concrete Pouring Coming Soon Things are coming along nicely at Bayne Park. The cement should be getting poured soon. Grand opening will be scheduled once the cement has cured. So….close…… Read More
Ramps are in place at Bayne Park The main ramps and ledges are in place as of today. Next comes the ground surface and rails. We will be skating this soon! It’s great to see the light at the end of the tunnel.… Read More
Continued Progress at Bellevue, PA Skate Plaza Location Progress continues at Bayne park in Bellevue. The foundation work has begun and things are looking good. I will take more photos as things continue to develop. Stay tuned! … Read More
Bellevue PA Skate Plaza Update There has been a slight delay on the foundation work for the skate plaza. We have been informed that the foundation concrete work will start on July 16th and the plaza will be skate-able by early August. Can’t wait! Here are some updated photos of the ground preparation… … Read More
Bellevue, Pa Skate Plaza Project Inspiration – Bethlehem Skate Plaza This video is an example of what skateboarders and city officials can do when constructively working together. We were able to accomplish this same goal in Bellevue and are now getting a skate plaza of our own. Construction of phase one is currently in the works. This could not have been done without the help from Bellevue council members,… Read More
Bellevue, PA Skateboard Plaza Ground Preparation I saw the Bellevue Borough workers working on the skate plaza location this morning, so I took a few quick video clips with my iPhone. It’s so exciting to see this plaza happening!!!… Read More
Day 01 – Old Surface Removal at Bayne Park Bellevue Borough began removing the old asphalt today at Bayne Park. This is step one in the skate plaza construction. Once the old asphalt is removed, the ground will be prepped and a new concrete foundation will be poured (roughly around June). Then the rest of the plaza will be constructed with hopes to be… Read More